EVMS Reporting Requirements
EVMS Reporting Requirements
CONTRACT VALUE |
APPLICABILITY |
NOTES |
SOURCE |
||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
< $20M |
Not required |
Integrated Program Management Data and Analysis Report (IPMDAR) may be used if cost and/or schedule reporting is requested by the program management office. | Integrated Program Management Data and Analysis Report (IPMDAR) DID DI-MGMT-81861* | ||||||||
≥ $20M & < $100M |
Required monthly when EVMS requirement is on contract |
All IPMDAR datasets/ files must be included in the CDRL. Tailoring in accordance with DI-MGMT-81861 and Implementation Guide is allowed. | Integrated Program Management Data and Analysis Report (IPMDAR) DID DI-MGMT-81861* | ||||||||
≥ $100M |
Required monthly when EVMS requirement is on contract |
IPMDAR is required. All files are required. | Integrated Program Management Data and Analysis Report (IPMDAR) DID DI-MGMT-81861* |
Table Notes:
All contracts, task orders, and delivery orders; IPMDAR data will be delivered to the EVMS Central Repository.
The IPMDAR can be tailored to collect cost and/or schedule data for any contract regardless of whether EVMS is required. For information on tailoring the IPMDAR, refer to the DoD IPMDAR Implementation Guide.
Formats and reporting requirements for the IPMDAR are determined and managed by the OUSD(A&S) Acquisition Data and Analytics.
For more information regarding the IPMDAR DID and Implementation Guide, or the EVM Central Repository, visit the OUSD(A&S) Acquisition Data and Analytics / Integrated Program Management website.
Reporting thresholds are in then-year dollars.
* DI-MGMT-81861 = Data Item Management-81861