Middle Tier of Acquisition (MTA)
Middle Tier of Acquisition (MTA)
INFORMATION REQUIREMENT |
SYSTEM TYPE |
SUBMISSION DUE |
SOURCE |
TYPE |
||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
NON-MAJOR SYSTEMS1 |
MAJOR SYSTEMS2 |
EXCEEDS MDAP THRESHHOLD3 |
||||||||||||||||
Acquisition Strategy, to include – security, schedule, technical, and production risks; a test strategy or an assessment of test results with validation of required cybersecurity and interoperability as applicable4; and a transition plan... |
|
x |
x |
At MTA Program Entrance |
DoDI 5000.80; DoDI 5010.44 |
Regulatory |
||||||||||||
ADM signed by the DA |
x |
x |
x |
At MTA Program Entrance |
DoDI 5000.80 |
Regulatory |
||||||||||||
Approved Requirement |
|
x |
x |
At MTA Program Entrance |
DoDI 5000.80 |
Regulatory |
||||||||||||
Cost Estimate5 |
|
x |
x |
At MTA Program Entrance |
DoDI 5000.80; DoDI 5000.73 |
Regulatory |
||||||||||||
Initial PID Entry |
x |
x |
x |
At MTA Program Entrance |
DoDI 5000.80 |
Regulatory |
||||||||||||
Lifecycle Sustainment Plan |
|
x |
x |
At MTA Program Entrance |
DoDI 5000.80; DoDI 5000.91 |
Regulatory |
||||||||||||
Written decision by USD(A&S) |
|
|
x |
At MTA Program Entrance |
DoDI 5000.80 |
Regulatory |
||||||||||||
Updated PID Entry |
x |
x |
x |
Throughout MTA Program Execution |
DoDI 5000.80 |
Regulatory |
||||||||||||
An assessment of test results |
x |
x |
x |
At MTA Program Exit |
DoDI 5000.80 |
Regulatory |
||||||||||||
Final PID capturing updated entries, to include the outcome, sustainment, and final budget of the MTA program |
x |
x |
x |
At MTA Program Exit |
DoDI 5000.80 |
Regulatory |
||||||||||||
Outcome determination ADM signed by the DA |
x |
x |
x |
At MTA Program Exit |
DoDI 5000.80 |
Regulatory |
Table Notes:
1 Equal to or below threshold as defined in Section 3041(c) and 4202(b) {formerly 2302d} of Title 10, U.S.C.
2 Above threshold as defined in Section 3041(c) and 4202(b) {formerly 2302d} of Title 10, U.S.C.
3 Defined in Section 4201 and 4202 {formerly 2430} of Title 10, U.S.C.
4 For initial submission, can use test strategy in lieu of assessment of test results if testing is not complete. For programs that are on the DOT&E oversight list, additional documentation may be required.
5 Per 5000.73: CAPE will conduct an estimate of life-cycle costs for programs likely to exceed ACAT I threshold pursued using the MTA rapid prototyping pathway. CAPE will conduct an estimate of life-cycle costs for programs likely to exceed ACAT I or II thresholds pursued using the MTA rapid fielding pathway.