    Does the FAR have a required time frame for construction/non-commercial items of 30 days or is that related to the $25,000.00 threshold only?


    Answer

    The FAR dose not have a required time frame. 

    Point to ponder:  Can you resonable have a solicitaion, conduct a site visit and expect contractor to give good proposal, and have adequete competion in less than 30 days? 

    Open full Question Details