    What is assumed on the DD1423 by having a Monday, 7th due date? How specific should due dates be on the DD1423? Now, knowing that all my CDRLs are already on Contract, how do I make sure that the deliverables are sent by the Navy's COB? Will I have to modify each 1423 or can I send a contracts letter?


    Answer

    This response is based on the original information and additional input from the submitter—

    The time difference may not be a significant matter. Let's assume the Government intends for the data items to be delivered by close of business (1700 hours) on Monday, but because of the time zone difference they are not delivered until 2000 hours.  The data items will still be there first thing the next morning, waiting for the interested Government personnel when they arrive. This does not seem to be a material issue for contract performance, and should probably be addressed as a management issue instead.