  • Question

    Can we legally use the OMA funds and fund each task order for less than $250K each and not be in a ADA situation. Do we need to use RDT&E funds or PRIP funds to create each report?


    Answer

    Since the reporting capability (6 additional reports) does not currently exist within the EDW and AIS structure, it appears that this is a capability enhancement to the current system.  Therefore, I would interpret this as a capability enhancement development effort.  Due to this, RDT&E funding would be required to develop the reporting capability in the above question.  Dollar value does not matter in this example - determination is based on whether or not it is a performance/capability enhancement and then if the system in question is still in production or not