    On following the template, for example i get to section 7.5 major contracts planned. The section wants you to address 16 sub-paragraphs. However 7.5 referecnce for a contract greater than 100M. My contract is far under this limit. Do i need to address the subparagraphs? Does this apply to all paragraphs that i dont meet the criteria, do i have to answer the subparagraphs?


    Answer

    The instructions for section 7.5 clearly state that 7.5, and by extension the subsections of 7.5, apply only for contracts exceeding $100 million. The other sections of paragraph 7, as well as other paragraphs and their sections in the template, do not limit their applicability based on a dollar threshold. You will need to address those paragraphs, sections, and subsections.