    Is there a some place in the FAR/DFAR/AFFAR where it provides guidance on progress reports for construction? I can't seem to find anything except production progress reports I was told that is not applicable to construction.


    Answer

    FAR Part 36 deals with Construction and Architect Engineer Contracts.

    Subpart 36.5 specifically talks about schedules for construction contracts and states that the clause at 52.236-15 may be inserted in fixed price construction contracts over the simplified acquisition threshold, with a period of performance over 60 days.  The clause outlines the specific time requirements for submitting a schedule as well as the format and content of the schedule and the consequences for failure to submit a schedule.  The does not contain additional coverage on construction contract schedules; however, you always need to review your agency regulations for specific agency related coverage.
     