    Is there a requirement when using 3400 funds for a new start project to process a waiver package to submit with the RFP in advance of an appropriation.


    Answer

    The organization would prepare a planning PR, which would include the appropriate coordination for their organization. The planning PR is then submitted to the contracting organization lead time away from contract award to allow them to issue the RFP. Once BA is available, then the planning PR is replaced with a funded PR (note: must be accomplished prior to contract award).