  • Question

    We have determined the following contractual remedies to address this issue. Are there any other remedies that could be used? Consideration for modifying the order to establish a new delivery date For product price Monetary compensation Covering shipping/packaging costs Providing early delivery free of charge Cure Notice (Allow a period of at least 10 days for the contractor to cure the failure(s)) Show-cause letter (Immediately stop work/ termination for cause) Partial/Full Termination for Default/Cause (noncommercial/commercial contract) Suspension or debarment


    Answer

    You have a robust list of possible remedies that is fairly complete. However, I recommend that you consult with your organization's legal counsel to determine which of these may be most appropriate to your specific situation.