    We were wondering if there was a table that existed that is simliar to the liquidated damages table.


    Answer

    There is no DoD wide construction period of performance table. Normally the period of performance is determined based on the circumstances of each construction project based on efforts required, location, anticipated weather, etc. Any table that does exist would be command specific as is the liquidated damages table you are referring to.  I believe that table is specific to NAVFAC.