Sign In
  • Question

    I have two questions: 1 - Can a RFP Letter replace section L of the contract? If so, does the RFP letter still have to include Section L provisions? 2. Is Section L and Section L provisions required in a RFP for a sole source delivery order? 3. why or why not?


    Answer

    Based on your questions - there are some assumptions i'm making:

    1. This is a Requirement/IDIQ  contract with the awardee being Sole Source and it's for supplies based on Delivery Order.

    2. Answer to your first question - Because it is not required - yes the RFP letter can replace Section L.

    3. Answer to the first question - second part - It's moot - because there is nothing to evaluate.

    4. Section L Provisions - are not required based on the assumption above. 