    Is the DPAP memorandum correct in regards to the contractor completing the rest of the attachment?


    Answer

    Per Defense Procurement & Acquisition Policy, the April 11, 2012 memorandum “Implementation of Government-Furnished Property Attachments to Solicitations and Awards” is no longer in effect.  PGI Part 245 (November 6, 2014) provides directions regarding GFP attachments.   In accordance with PGI 245.103-73, the contracting office is responsible for preparing GFP attachments using the procedures in PGI 245.103-72.  However, the contracting officer is not precluded from requesting the contractor’s assistance in populating the attachments. 