    Does the government have to evaluate this single CRNF CLIN for Over and Above Work as part of the Source Selection?


    Answer

    In order to evaluate all proposals for cost the answer would be yes, the government would have to compare all contractor proposals in the same way. This information should be expressed in section L and M of the solicitation.  If all contractors will be required to propose and over and above work CLIN, and it is not stated as a standard amount for all proposals, then it should be evaluated as part of the cost trade-off evaluation. 