    This is an AbilityOne contract and the renewal is going to the same AbilityOne Contractor. Are there any known implications if the current contract is modified to extend the current contract POP past the 52.217-8 6 month extension.


    Answer

    First, you should put every effort into awarding your follow-on contract on time.  You must do the proper documentation on this and modify the contract by mutual agreement of the parties.  Because it is a modification to an AbilityOne contract, you do not have to do a J&A (exception at FAR 6.302-6(c)(2)(i) or synopsis (FAR 5.202(a)(4) exception).  You still must find the price to be fair and reasonable.