    Is there a way to combine different scope task orders into one task order moving forward (possibly as a modification?) or do I have to relay to the program office that combining task orders of different scopes is not possible?


    Answer

    From the details given and since the question said task orders, these are service contracts with options the organization wants to have exercised.  They are no longer task orders, they are two separate contracts for different types of services.  Exercising the options does not turn them back into task orders, exercising the options will extend both of the contracts if the options are for extending time.  You will not be able to write a modification saying the two contracts are now one contract. 