    In a case such as this, can the SBA issue an administrative modification to correct the Period of Performance.


    Answer

    The contract specialist can issue an administrative modification to correct the period of performance if it was truly an error at the time of issuance.  Since your original order was done in 2012, you would want to work with the contractor to determine if period of performance was truly an error and to see if the contractor is no longer working the call order since you are saying it should have ended in 2013.