  • Question

    Is there any contract closeout procedure that requires processing a contract modification to delete contract CLINs or SubCLINs that were anticipated and included in the initial contract award but never resulted in contractor performance?


    Answer

    I can think of no reason to delete unused CLINs or SLINs, nor is it a requirement of FAR subpart 42.7. It is also not listed on the DoD contract closeout checklist, DD Form 1597 as an element to be completed.
     
    It would be similar to deleting an option that wasn't exercised- just no need to do it.
     