    If this were awarded as a FFP IDIQ, how would I go about removing the lines we no longer need from each Task Order? If this were a FFP C contract with "optional" CLINs, again how would I go about removing the cable lines when we no longer need them? Either way, would we just have to do a bilateral modification/partial termination? What contract type or CLIN structure would provide the flexibility needed for this requirement?


    Answer

    Yes, you would simply do a partial termination, though it would be a unilateral rather than bilateral modification. Also note that a requirements type contract could provide even more flexibility than an IDIQ, as the Government would not be liable for a minimum quantity of cable lines.