  • Question

    Is it required that we write a Determination and Findings (D&F) for establishing a performance based CLIN to be signed by the Contracting Officer (or a higher level authority). Do you have a sample D&F available? Where would the direction be that requires a D&F be written? Thank you, John


    Answer

    FAR 16.401(d) establishes the requirement to complete a determination and finding (D&F) for incentive type contracts, to be signed by the head of the contracting activity. FAR 1.704 contains the content requirements for the D&F.