    Does Budget Activities in the Research and Development section of an LCCE determine (or impact) an ACAT Level? Or Is ACAT Levels determined by Research and Development costs rebaselined to FY14 Dollars?


    Answer

    No, budget activities DO NOT determine the ACAT Level.  ACAT level is determined by either total RDT&E or procurement appropriations for the program.  See DoDI 5000.02, Enclosure 1, Table 1, for threshold values.  See also the answer to Question #126268, which also covered this topic.