  • Question

    After reviewing the LCCE with my respective Program Manager and the respective APB, he would like to apply a 20% Threshold value to the APUC and PAUC versus the standard 10% value since the production prices are fuzzy and pretty far out for the program. This would be our rationale. So my question is, after reading the DoDI 5000.02, can we apply the 20% Threshold value to the APUC and PAUC without a Statutory Program Breach (Table 4 of the DoDI 5000.02) and a Significant or Critical Nunn-McCurdy Cost Breach of 15 and 25 percent respectively? Thx Chris Soltez Program Analyst JPEO JPM NBC Contamination Avoidance E2800 Edgewood APG, MD P:410-417-3440


    Answer

    The statutory guidance in DoDI 5000.02 Table 4 WRT Significant and Critical Nunn-McCurdy Unit Cost Breaches per 10 U.SC. 2433 and 2433a applicable to MDAP is clear. The program office doesn't have authority to modify statutory guidance. For further clarification I recommend you discuss with your legal office."