  • Question

    Does the customer have to do a new IGE or can they just extract the TASK and do an IGE for that portion and summarized the original IGE, changing the overall estimate by adding the sub-total of the task to the Summary?


    Answer

    There is nothing that states the customer needs to do a new IGE; however, the IGE should be appropriately updated to accurately show the change in the level of effort and the estimated costs that are associated with the required change. 