    Once the performance period has ended on an IDIQ contract can a J&A be executed to extend the performance period and ordering period so that a delivery order can be issued to for this new work?


    Answer

    Since the contract has not been closed out, it is still technically "open, but ready for closeout". A J&A would be necessary to extend both the ordering and performance period. In effect, you are authorizing a new contract, and for administrative convenience, attaching to the current "open" vehicle.