    So my question here is whether or not there is a reference that specifically allows or disallows a cost-reimbursement contract's voucher review and approval to be delegated to a COR at the EPA. I'm also curious if the answer is now the same at DoD and other agencies. Thanks!


    Answer

    Contracting officers in DoD have always been allowed to delegate review of vouchers on CR contracts.  However, they are still not allowed to delegate approval ("certification" is used interchangeably in DoD with approval) of interim vouchers on CR contracts.