    I am not a procurement or contracts person. I am a program manager. Due to the time constraints can I solicit suppliers and ask for pricing and availability of equipment or must I run all requests through our procurement and contracts group? Thank you


    Answer

    This response is based on the information provided.  We suggest you discuss with your contract administrator and/or legal department and the government contracting officer as appropriate. 
     
    The FAR has no requirement as to who requests, develops cost support information, i.e. quotes, engineering estimates etc.  What the DoD requires is that what a company submits is accurate ,current and complete.  Developing a proposal submission should be done within company procedures.