  • Question

    Is this correct and where do I fine the authority for such action.


    Answer

    The Consolidated Project Plan (CPP) is an organizational unique artifact for program planning.  The Department of Defense Instruction (DoDI) 5000.02 directs use of a Life Cycle Sustainment Plan (LCSP), including ACAT III programs for continuity, enclosure 2 is germane.  Specifically, the aforementioned Instruction (Enclosure 6) provides “ Program Managers for all programs are responsible for developing and maintaining an LCSP consistent with the product support strategy, beginning at Milestone A.” 