    Two Questions: 1. I'm looking for the publication dates of the EIA 748 Revision C and a copy of the document. 2. Is an EVMS system required for primarily a time and material service contract where man hours are being paid for maintenance support? This is not a production contract.


    Answer

    1. The document can be found at this link.
    2. Per DFARS 234.201, EVMS is required for cost or incentive contracts valued at $20 million or more. Time and materials contracts are not among the required contract types.