Sign In
  • Question

    Can both Suppy and recurring Service requirements consolidate into RFQ/PO as an one requirement?


    Answer

    This response is based on the information provided.  We suggest you discuss with your contracting team, program manager and/or legal department as appropriate. 
     
    There is nothing in the FAR/DFARS/AFFARS that precludes putting this effort into one contract action.  When doing so,  a minimum of three CLINs is necessary.  One CLIN would be for the ANALYZER and would likely be firm fixed-price.  A second CLIN would be for ROUTINE MAINTENANCE and would also likely be firm fixed-price.  The third CLINB would be for UNSCHEDULED MAINTENANCE/REPAIR and would likely be Time and Material.
     

    Open full Question Details