    When constructing or relocating a structure or fencing, does 52.236-5 apply?


    Answer

    The prescription at FAR 36.505 states, "The contracting officer shall insert the clause at 52.236-5, Material and Workmanship, in solicitations and contracts for construction contracts."  FAR 52.301 -- Solicitation provisions and contract clauses (Matrix) specifies that FAR 52.236-5 is required for Cost Reimbursement Construction contracts