  • Question

    Is it appropriate to conduct an ASP briefing for a follow-on services contract? Specifically, is it appropriate for a SCAT IV contract?


    Answer

    Yes, AFFARS 5307.104-92(a)(3) states,  "For other contract actions ASPs must be convened for all acquisitions that require an AP."

    You would also want to examine AFI 63-138, DoD5000.74, and seek the advice of your branch COCO and legal.