    Is PSC D322 Exempt from requiring a COR


    Answer

    There is no automatic exemption for a COR to be designated based on the PSC of the contract action.  The guidance for when a COR is needed to be assigned/designated is in:

    DFARS PGI 201.602-2(d) (v)(A)

    There is a chance your contract action meets all of the the conditions identifed and won't need a COR.  But remember, it must meet all three of the requirements.