This response is based on the information provided. We suggest you discuss with your contracting team, program manager and/or legal department as appropriate.
We believe you are correct to document the actions you are taking. If the contracting officer was incrementally funding a firmed fixed-price contract, that was likely incorrect and, without knowing if there are other circumstances, potentially anti-deficient.
Your legal advice was also correct. We use a J&A to support doing other than full and open competition. But you need to have a determination and findings in the record, particularly given the circumstance you are amending.