    Where is it in writing that the contractor has 30 days to provide the Contracting Officer their CAP and that the Contracting Officer has 15 days to approve or decline the CAP and once the CAP is approved the contractor has 45 day to implement their new procedures?


    Answer

    The relevant timeframes are contained in para. (d) of the clause at DFARS 252.245-7003 (Contractor Property Management System Administration). Of course, if a different version of the clause is contained in the contract, the timeframes therein would apply instead.