I see no timeline specified in the procedures section at FAR 8.705. The only time period specified is for an order is delayed when the purchase is made using the direct allocation process (8.705-3), but that doesn't apply to you. In the absence of specific guidance, the solicitation guidance at FAR 5.203 would apply.