    Can an agency create a MACC by awarding the base contracts using the 8(a) sole source process to select the contractors on the MACC, if the value of the MACC is less than the 8(a) competition threshold of $4.5 million?


    Answer

    No. The  nature of a multiple-award contract is involving multiple contractors and fair opportunity IAW FAR 16.505(b) comes into play with the orders under the MAAC after award of the base contract. Awarding an 8(a) sole source would make an IDIQ a single award IDIQ, and therefore not multiple award. 

     