    When is a price matrix required when issuing a solicitation for services? Who is responsible for creating the price matrix?


    Answer

    In absence of clarification from the questioner, we'll answer generically.

    Question 1:  When is a price matrix required when issuing a solicitation for

    services?  When the acquisition team wants information in a certain format.

    For example, when the team desires that a excel spreadsheet be populated to calculate the

    total evaluated price (TEP) or if there is a government provided rate

    schedule that needs to be populated for all the applicable contract periods.

    The rates will be used to evaluate price based on scenarios during the

    source selection evaluation phase and to price out future task orders

    depending on the contract structure. The acquisition situation drives

    whether or not a price matrix is required and the acquisition team drives

    the structure of the matrix, i.e.  what information they want and in what

    format they want it.

     

    Question 2. Who is responsible for creating the price matrix? The

    contracting officer with help from the price/cost analyst if there is one available. 