    How long do we need to wait before modifying or adding on to the new facility?


    Answer

    If this is a true new unknown requirement there is not a time limit.  This new requirement should not have been known at the orginal time of construction.  The new need should be a new unit, new mission, etc. 

    Looking at this it sounds like your are trying to increment this construction; that is illegal. You would have to wait at least 5 years before adding to the facility.  If you don't think this will pass an Inpsector General inspection, don't do it.  This should have been programed under the MILCON.