    On the same contract modification, can funds from the underrun CLIN be moved to fund the overrun CLIN if there have been within scope changes to the one or both CLINs? (Note: I reviewed all 1,000 questions and none answer my above question.)


    Answer

    I have done exactly that as a contracting officer many times- sometimes the lawyers said I could not do it, and sometimes other lawyers said I could. A solution would be to execute an administrative mod, where you are just "correcting" the line item funding numbers.
     