    Is there another clause I should include in Construction solicitations/contracts that states that we will award without discussion, or is that necessary? Why would that clause not also apply to Construction solicitations/contracts? Thanks!


    Answer

    Yes there are other (more appropriate) clauses; you should use Federal Acquisition Regulation (FAR) clause 52.214-18 -- Preparation of Bids – Construction in your Invitation for Bids (IFB).  Also, use the FAR clause 52.214-19 -- Contract Award -- Sealed Bidding – Construction, which states (in part) “… (a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract …”