    What exemption did you used for commercial item?. According to FAR 15.402 data other than certified cost or pricing data such as data obtained from the offeror can be used to establish fair and reasonable price. The contractor did submit a detail price breakdown which is sufficient to determine a fair and reasonable price. Is this sufficient? Have any of you requested certified cost and pricing data from SBA for an 8a firm? If so, how long is the process?


    Answer

    The object is to determine if the sole source price is fair and resonable.  A detailed price breakdown should be sufficient for this type of Firm Fixed Priced contract. 

    I have never obtained the cost and priceing data from SBA.  You should ask SBA about their timeline.