    Is the contract entitled to the fully negotiated fee or only the incremental portion of the fee.


    Answer

    There are a number of bigger issues here- Was performance allowed to continue in the absence of funds? If so, you may have an Anti-Deficiency Act violation on your hands. Is the contractor entitled to a termination for convenience?
     
    These major issues aside, I would agree that the task orders are completion type efforts- but again these other issues are paramount and must be resolved first.