Sign In
  • Question

    Can data deliverables called for in the contract be delivered via "contracts letter" or should they be delivered through CDRL? What is the tipping point for inclusion in exhibit when the data is Non-Technical?


    Answer

    To the best of our understanding, there is not a requirement for these to be delivered as CDRLs.  It is recommended that the contracting office make the final call here, as they are ultimately responsible for the contractor-government relationship.  The bottom line:  If both parties agree either approach is acceptable.
     
    Please let us know if you have further questions.

    Open full Question Details