    What are the advantages on going "Best Value" LPTA on the main award?


    Answer

    As always it is a contracting officer's recommendation to go either Best Value or LPTA.  Following Part 15, with your Acquisition team members (especially technical) you must determine if you will need trade-offs to get to final award.  If so, then Best Value.  If you have true competition and most contractors will give you much the same "answer" technically, so the only thing you are really concerned with is price, then LPTA.

    Please remember, the staffing and timeline for a Best Value will be more than for an LPTA.