  • Question

    My question is can you really do this? I have argued no because I feel the MILCON appropriation included the Communications wire as part of the programmed amount and therefore it is part of the building. To build a complete and usable building would include using the wire.


    Answer

    No you cannot purchase using O&M.  You cannot mix O&M and MILCON.  You will need to meet your requirement on your 1391.  If you are in  a budgetary constraits, you may need descope some optional items.  If you can't you will need to request additional MILCON funds.

    Open full Question Details