    Does the issuance of an in-scope modification adding work to the already-behind-schedule contract in effect negate the Government's liquidated damages entitlement for unexcused late completion?


    Answer

    LDs are enforceable.  In this situation LDs will be part of the negotiation on the pending modification. 