  • Question

    Should I keep the start date 09/27/2010 - 08/31/2012, explaining the purchase order has been extedned for an additional 12 months.


    Answer

    You keep the 2010 start date and state the period of performance was extended for 11+ months. If you change the start date to 2011 and you used 2010 funds to originally fund the procurement, it may give the appearance of an Anti-deficiency violation.