APMT 037

DAU GLOSSARY DEFINITION

Contains data for measuring cost and schedule performance on Department of Defense (DoD) acquisition contracts. It is structured around seven formats that contain the content and relationships required for the electronic submissions. It includes seven formats: Format 1 defines cost and schedule performance data by product oriented Work Breakdown Structure (WBS)  Format 2 defines cost and schedule performance data by the contractor's organizational structure (e.g., Functional or Integrated Product Team (IPT))  Format 3 defines changes to the Performance Measurement Baseline (PMB)  Format 4 defines staffing forecasts  Format 5 is a narrative report used to provide the required analysis of data contained in Formats 1-4 and 6  Format 6 defines and contains the contractor's Integrated Master Schedule (IMS)  Format 7 defines the time-phased historical and forecast cost submission.

Alternate Definition

The Integrated Program Management Report (IPMR) A contractually required report, prepared by the contractor, containing performance information derived from the internal Earned Value Management System. Provides status of contract cost and schedule performance (DI-MGMT-81861). Effective Apr 22, 2020, IPMR has been superceded by the Integrated Program Management Data and Analysis Report (IPMDAR)

Alternate Definition Source

DoD Earned Value Management System Interpretation Guide (EVMSIG)

General Information

USD(AT&L) Memo: Integrated Program Management Report (IPMR) Data Item Description (DID), June 19, 2012 established the IPMR. As directed in this memo, for all future contracts that are awarded based on solicitations or requests for proposal issued on or after July 1,2012, the IPMR supercedes both the CPR and IMS DIDs. (Note: Contracts issued prior to this date will continue to use CPR and IMS DIDs. It will not be necessary to modify existing contracts.) 

USD(A&S) Memo: Integrated Program Management Data and Analysis Report (IPMDAR) Data Item Description (DID), Apr 22, 2020 established the Integrated Program Management Data and Analysis Report (IPMDAR). As directed in this memo, for all contracts that are awarded based on all applicable solicitations or requests for proposal issued after the memo date, the IPMDAR will supercede both the CPR, IMS, and IPMR DIDs. (Note: Contracts issued prior to this date will continue to use CPR, IMS, or IPMR DIDs. It will not be necessary to modify existing contracts.)

The IPMR was structured around seven formats that contain the content and relationships required for the electronic submissions.

  • Format 1 provides cost and schedule performance data by product oriented Work Breakdown Structure (WBS).
  • Format 2 provides cost and schedule performance data by the contractor's organizational structure (e.g., Functional or Integrated Product Team (IPT)).
  • Format 3 provides changes to the Performance Measurement Baseline (PMB).
  • Format 4 provides staffing forecasts.
  • Format 5 is a narrative report used to provide the required explanations of changes and analysis of data contained in Formats 1-4 and 6.
  • Format 6 defines and contains the contractor’s Integrated Master Schedule (IMS).
  • Format 7 defines the time-phased historical & forecast cost submission.