Work Package (WP)

DAU GLOSSARY DEFINITION

Natural subdivision of a control account. A work package is simply a task/activity or grouping of work and is the point at which work is planned, progress is measured, and earned value is computed. It can be translated into different terms in different companies and functions. It can be a design job, a tool design package, a build-to-package, a shop order, a part number, a purchase order, or any other definable task/activity at whatever level of control is normal for program management within the company.

Alternate Definition

A Work Package (WP) is a natural subdivision of Control Accounts (CA) . A WP is simply a task/activity or grouping of work. A WP is simply a task/activity or grouping of work. A WP is the point at which work is planned, progress is measured, and earned value is computed.

Alternate Definition Source

DoD Earned Value Management System Interpretation Guide (EVMSIG)

General Information

A Work Package (WP) can be translated into different terms in different companies and functions. It can be a design job, a tool design package, a build-to-package, a shop order, a part number, a purchase order or any other definable task/activity at whatever level control is normal for program management within the company.

 

Work packages (WPs) are best explained by understanding their relationship with the Performance Measurement Baseline (PMB) .

Figure 1

The Performance Measurement Baseline (PMB) consists of three elements. The first is the Undistributed Budget (UB). This is a temporary holding budget that should be allocated as soon as practical to either the second PMB element, control accounts (CAs), or the third element, Summary Level Planning Packages (SLPPs) . SLPPs are traditionally established for far term work. For near term and well defined work, earned value CAs are established. A CA is further subdivided into Work Packages (WPs) and Planning Packages (PPs) A CA may have hundreds of WPs and PPs . An EVM concept called a rolling wave is often used to move work from SLPPs to CAs and from CA PPs to more detailed CA WPs .