DoD Integrated Product Support Implementation Roadmap – Timeline View

    MDD Materiel Solution Analysis   MS A Technology Maturation & Risk Reduction   MS B Engineering and Manufacturing Development   MS C Production and Deployment     Operations and Support  
  Activities Outputs Activities Outputs Activities Outputs Activities Outputs Activities Outputs
Major Program Key Events/Products

ICD

POM Input

TEMP

ICE

AoA

RFP

Milestone Documentation

Spectrum Certification Compliance

CARD

ADM

DAB Review

SEP

CONOPS

ACAT Designation

IPS (input to the RFP)

Exit Criteria

CCA Compliance

Acquisition Plan

Economic Analysis

Component Cost Estimate (CCE)

Cybersecurity

Draft CDD

SEP

Milestone Documentation

Acquisition Plan

CORE

Acquisition Strategy (input to the RFP)

LCC

TEMP

CCA Compliance

LCSP

APB

ADM

RFP

Post-CDR/PDR Report

CCE

Allocated Systems Baseline

AoA

DAB Review

Corrosion Prevention Control Plan

EVMS

ILA

Independent TRA/TRA

Independent Review and Assessment

CCDR

PESHE/NEPA

Exit Criteria

Spectrum Supportability Determination

Program Protection Plan (PPP)

Spectrum Certification Compliance

Service Cost Position (SCP)

ACAT Designation

Cybersecurity

BCA

ADM

Acquisition Plan

CCA Compliance

CCE

CCDR

CORE

AoA

LRIP Source Selection

Initial Product Baseline

Spectrum Supportability Determination

Corrosion Prevention Control Plan

Independent TRA/TRA

Spectrum Certification Compliance  

Cybersecurity

LCC Estimate

CPD

ACQ Strategy

BCA

ISP

Milestone Documentation

SEP

APB

TEMP

EVMS

ICE

CARD

LCSP

ILA

Program Protection Plan (PPP)

PESHE/NEPA

Exit Criteria

DAB Review

LRIP Contract

RFP for Production Contract

IOT&E  

Cybersecurity

DAB Review

IOT&E Report

Final Production Baseline

CPD

APB

ACQ Strategy

Major Modifications/System Improvements

CCE

System Fielding (H/W/S)

TEMP

New DOTMLPF Change Recommendation (DCR)

CCDR

FRP Contract

Beyond LRIP Report

Program Protection Plan (PPP)

CARD

Acquisition Plan

AoA

Exit Criteria

LCSP

ADM

Component LFT&E Report

ILA

EVMS

CCA Compliance

IOT&E Report

IOT&E Completed

SCP

ICE  

Cybersecurity

Product Support Management

Ensure Logistics trade studies/market research are incorporated in AoA and forecast product support for each alternative

Identify Support and Maintenance Concepts and Technologies

Develop initial Product Support inputs to Life Cycle Sustainment Plan (LCSP)

Recommend Product Support Requirements for inclusion in the ICD

Evaluate New and Existing Product Support Capabilities

Identify Initial Sustainment Metrics

Identify supportability risks/cost drivers

Conduct supportability risk assessment/mitigation

Develop initial supportability WBS/IMS

Assess replaced system Product Support Package for applicability to new capability

Develop Funding Requirements to Execute Product Support Concept

Identify/Charter Product Support Team

Incorporate initial support test strategy into TEMP

Develop initial Product Support inputs to HSI plan

Identify product support requirements for inclusion in the RFP

Participate in source selection and evaluation

Support PM in preparation for Defense Acquisition Board (DAB) Review

Initial Life Cycle Sustainment Plan (LCSP)

Product Support Alternatives (Included in AoA)

Initial Funding Requirements for Product Support Concept (ICE, LCCE, CARD)

Initial Product Support Concept (Included in IPS/AS)

Product Support IMS

Product Support Test Strategy (Included in TEMP)

Product Support Requirements (Included in RFP)

Recommend Product Support Requirements (included in the ICD)

Sustainment Metrics

Product Support inputs to:

Milestone Decision - MS A

Update Life Cycle Sustainment Plan (LCSP) from Initial Support Strategy

Update Supportability Risk Assessment and Identify Mitigation Strategy

Influence Design for Supportability through participation in technical/program reviews

Develop Initial Disposal Strategy

Develop Fielding Strategy

Include CORE, 50/50, DSOR/SOR

Intellectual Property Strategy (IPS)

Update Funding Requirements to Execute Life Cycle Sustainment Plan ';>;EndMetacard

Collect and collate IPS elements Supportability Requirements in support of RFP

Participation in source selection evaluation process

Update Inputs to HSI plan

Update Product Support Integrated Master Schedule (IMS)

Recommend Product Support Requirements for inclusion in the CDD

Update Product Support BCA

Develop supportability events for TEMP

Support PM in preparation for Defense Acquisition Board (DAB) Review

Life Cycle Sustainment Plan (LCSP)

Product Support IMS (Included in Program IMS)

Logistics/Supportability Portions of the: Performance Spec, WBS and SOW/SOO (Input to RFP)

Revised Funding Requirements to Execute LCSP

Supportability Testing Events (Included in the TEMP)

Product Support Requirements (Included in the CDD)

Initial Disposal Strategy

Fielding Strategy

Product Support inputs to:

Milestone Decision - MS B

Ensure Participation in Logistics/Technical/Program Reviews

Collect and collate IPS elements Supportability Requirements in support of RFP

Participate in source selection process

Fielding/Deployment Plan, Disposal Plan, CORE, 50/50

Update Funding Requirements to Execute Life Cycle Sustainment Plan

Incorporate supportability testing procedures in the TEMP to include pass/fail criteria

Product Support Test Package for DT/OT and supportability testing

Update Product Support BCA

Identify Product Support Integrator(s)

Intellectual Property Strategy (IPS)

Update Inputs to HSI Plan

Update Life Cycle Sustainment Plan (LCSP)

Provide Product Support Requirements in the CPD

Support PM in preparation for Defense Acquisition Board (DAB) Review

Life Cycle Sustainment Plan (LCSP)

Draft Fielding/Deployment Plan

Validated Product Support Package

Supportability Requirements (included in the CPD)

Revised Funding Requirements to Execute LCSP (included in the updated LCCE/POM)

Logistics/Supportability Portions of the: Performance Spec, WBS and SOW/SOO (input to LRIP RFP)

Product Support Requirements (included in the CPD)

Product Support Integrator(s) identified

Draft Disposal Plan

Product Support inputs to:

Milestone Decision - MS C

Ensure Participation in Logistics/Program/Technical Reviews

Update Fielding Plan

Product Support Test Package for IOT&E and supportability testing

Collect and collate IPS elements Supportability Requirements in support of RFP

Participate in source selection process

Conduct Supportability Demonstration

Post Deployment Reviews

Update Life Cycle Sustainment Plan (LCSP)

Update Disposal Plan

Develop Performance Based Agreements with PSI

Update Inputs to HSI Plan

Update Funding Requirements to Execute Life Cycle Sustainment Plan

Update Product Support BCA

Update Product Support IMS

Support PM in preparation for Defense Acquisition Board (DAB) Review

Life Cycle Sustainment Plan (LCSP)

DMSMS Plan (from Supply Support, Sustaining Engineering, Design Interface, Maintenance Planning and Management)

Intellectual Property Strategy that addresses Technical Manuals, Engineering, Data, Bills of Materiel (from Technical Data, Sustaining Engineering, Design Interface, Support Equipment)

Training Program (from Training and Training Devices, Facilities and Infrastructure, Maintenance Planning and Management)

Depot Maintenance Capability (Maintenance Planning and Management, Facilities and Infrastructure, Product Support Management)

PD Software Support (Computer Resources)

Supportability FRP Source Selection

Revised Funding Requirements to Execute LCSP

Validated Product Support Package

Final Fielding Plan

Product Support Contracts and Agreements

Product Support inputs to:

Milestone Decision Full-Rate Production (FRP)

Execute System Fielding Plan

Execute Life-Cycle Sustainment Plan (LCSP)

Proactive System Performance Management

MTBF analysis

Causal factors analysis

Obsolescence Management

Sustaining Engineering

CBM+

RCM

COA Development/Implementation

System Performance Measurement (KPPs and KSA)

Intellectual Property Strategy (IPS)

Update inputs to HSI plan

Update Product Support IMS

Update Product Support BCA

System Disposal - Update Plan

Warfighter Received Total System

Post Fielding Evaluation

System Modifications (ECP)

System Improvements

New System Increment

Disposed Systems

Maintenance Planning and Management

Review ICD to identify maintenance requirements and support KPPs and KSAs

Lead Development of Maintenance Strategy inputs to LCSP

Develop Maintenance Planning and Management requirements for inclusion in RFP

Participate as a Maintenance Planning and Management SME advisor to the source selection process

Develop the preliminary maintenance planning and management IMS

Develop preliminary Maintenance Planning and Management Concept

Develop Funding Requirements to Execute Maintenance Planning Concept

Participate in initial use study

Prepare Initial input to RAM-C Rationale Report

Develop Initial Maintenance concept inputs to HSI plan

Maintenance Planning and Management Concept

Maintenance Planning and Management IMS

Maintenance Planning inputs to:

Review CDD to identify maintenance concepts

Support planning for and conduct of system level analyses

Develop initial Maintenance Strategy

Research DSOR/SOR impacts

Research CORE (50/50) impacts

Conduct supportability analysis to influence design

Complete 1st iteration of the RCM Analysis

Update RAM-C Rationale Report

Update the maintenance planning and management IMS

Lead development of Maintenance Planning and Management inputs for the LCSP

Participate in technical and programmatic reviews

Update maintenance planning and management requirements for inclusion in RFP

Participate as a SME advisor to the source selection process

Provide Maintenance Planning and Management inputs to Product Support BCA update

Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

Maintenance Strategy

Maintenance Planning inputs to:

Develop Maintenance Plan

Update system supportability analysis

Review updated use study

Lead Maintenance Task Analysis review with IPSE SMEs

  • Preventive and corrective maintenance tasks identified using RCM and CBM+
  • Review FMECA and LORA data to support maintenance planning decisions
  • Provide Maintenance Planning and Management inputs to Product Support BCA update

    Update maintenance planning and management requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update HSI Plan

    Update the maintenance planning and management IMS

    Update maintenance planning and management information in LCSP

    Participate in technical and programmatic reviews

    Maintenance Plan

    Updated system supportability analysis

    Maintenance Planning inputs to:

    Update maintenance planning and management requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update Maintenance Plan

    Update inputs to the LCCE Funding Statement

    Update the maintenance planning and management IMS

    Update maintenance planning and management inputs to the LCSP

    Participate in technical and programmatic reviews

    Provide support to Product Support BCA

    Updated Maintenance Plan

    Updated system supportability analysis

    Maintenance Planning inputs to:

    Execute Maintenance Plan

    Update inputs to the LCCE

    Update the maintenance planning and management IMS

    Update maintenance planning inputs to the LCSP

    Proactive System Performance Management

    Updated system supportability analysis

    Maintenance Planning inputs to:

    LCSP

    Prognostics and Health Management

    QDR

    ECP/ECR

    Corrosion Control

    Design Interface

    Ensure membership of appropriate IPTs (SE, Test, Product Support, etc)

    Develop the preliminary design interface IMS

    Participate in the Alternative Systems Review (ASR)

    Conduct AoA

    Participate in initial Use Study

    Review ICD to identify design interface requirements and support KPPs and KSAs

    Develop initial design interface inputs to LCSP

    Develop design interface requirements for inclusion in RFP

    Participate as a Design Interface SME advisor to the source selection process

    Develop preliminary design interface concept

    Develop Funding Requirements to Execute design interface Concept

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial design interface concept inputs to HSI plan

    Initial functional analysis cost estimates

    Preliminary design interface concept

    Product support alternatives

    RAM-C Report

    Inputs to the LCSP

    Design Interface inputs to:

    Review CDD to identify design interface concepts

    Update design interface requirements for inclusion in RFP

    Participate as SME advisor to the source selection process

    Update the design interface IMS

    Evaluate product support metrics

    Develop Design Interface inputs to LCSP

    Inputs to DMSMS Plan

    Support planning for and conduct of system level analyses

    Develop initial design interface strategy

    Research DSOR/SOR impacts

    Research Depot Maintenance CORE and 50/50 impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Participate in technical and programmatic reviews

    Provide design interface support to Product Support BCA update

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    Updated functional analysis cost estimates

    Design interface strategy

    Initial FMECA

    Design interface inputs to:

    Participate and provide input to the generation of CPD in support of PSM

    Update design interface requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the design interface IMS

    Perform an updated RCM Analysis

    Update Design Interface inputs to LCSP

    Participate in the SE led development of the Reliability Growth Plan

    Monitor and assess OEM submitted waivers and deviations for product support impacts.

    Participate in technical and programmatic reviews

    Contribute to the generation of Detailed Test Plans

    Parts and materiel selection

    RAM and Quality MOEs

    Design limit testing

    Manufacturing plan screening

    HMC&M/ESOH Compliance Plan

    Provide updates to PSM risk assessment

    Update inputs to SEP

    Update inputs to DMSMS Plan

    Update system supportability analysis

    Provide Design Interface inputs to Product Support BCA update

    Update HSI Plan

    Establish Configuration Management Plan

    Update functional analysis cost estimates

    Updated FMECA

    Updated Maintenance Task Analysis

    Updated design interface strategy

    Updated system supportability analysis

    Design Interface inputs to:

    Configuration Baseline

    Update design interface requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the design interface IMS

    Provide input to PSM risk assessment

    Update design interface chapter of LCSP

    Provide input to requirements documents for future increments and capabilities

    Participate in technical and programmatic reviews

    Contribute to the generation of Detailed Test Plans

    Provide support to Product Support BCA

    Update CM Plan

    Updates to RAM-C Report

    Identified Risks

    Updated system supportability analysis

    Design Interface inputs to:

    Responsibility for supportability engineering (e.g., configuration management, reliability, ECP/ECR) at this stage of the program's lifecycle transitions to the Sustaining Engineering IPS Element.

    Sustaining Engineering

    Responsibility for supportability (e.g., configuration management, reliability, ECP/ECR) at this stage of the program's lifecycle is Design Interface IPS Element.

    Sustaining Engineering

    Responsibility for supportability (e.g., configuration management, reliability, ECP/ECR) at this stage of the program's lifecycle is Design Interface IPS Element.

    Sustaining Engineering

    Responsibility for supportability (e.g., configuration management, reliability, ECP/ECR) at this stage of the program's lifecycle is Design Interface IPS Element.

    Sustaining Engineering

    Responsibility for supportability (e.g., configuration management, reliability, ECP/ECR) at this stage of the program's lifecycle is Design Interface IPS Element.

    Sustaining Engineering

    Update inputs to the LCCE

    Update the Sustaining Engineering IMS

    Update and Execute Sustaining Engineering in LCSP

    Proactive System Performance Management

    Most recent update to RCM Analysis

    Supportability testing information (plans, metrics, results)

    Prognostics and Health Management

    QDR

    ECP/ECR

    Corrosion Control

    Supply Support

    Participate as a SME advisor to the source selection process

    Develop the preliminary Supply Support IMS

    Review ICD to identify supply support requirements and support KPPs and KSAs

    Develop initial supply support inputs to LCSP

    Develop supply support requirements for inclusion in RFP

    Develop preliminary Supply Support concept

    Develop Funding Requirements to Execute Supply Support Concept 

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial Supply Support concept inputs to HSI plan

    Supply Support alternatives

    Risks and cost drivers for supportability

    Supply Support IMS

    Supply Support inputs to:

    Prepare SOW/SOO with appropriate DIDS/CDRLS for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update the supply support IMS

    Select preferred Supply Support strategy

    Develop Supply Support inputs to the LCSP

    Participate in technical and programmatic reviews

    Identify and analyze Supply Support alternatives, risk and cost drivers

    Develop Draft Disposal Plan

    Review CDD to identify supply support concepts

    Support planning for and conduct of system level analyses

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Provide support to Supply Support BCA update

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    Supply Support Strategy

    Supply Support inputs to:

    Prepare SOW/SOO with appropriate DIDS/CDRLS for inclusion of production contract

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the Supply Support IMS

    Participate in technical and programmatic reviews

    Update Supply Support Plan

    Conduct provisioning planning conference

    Review Capabilities Development Document and Refine Supply Support

    Provide Supply Support inputs to validation of product support package

    Draft Fielding Plan

    Use LORA to determine impacts on Supply Support strategy

    Update system supportability analysis

    Review updated use study

    Provide Supply Support inputs to Product Support BCA update

    Update HSI Plan

    Update Supply Support requirements for inclusion in RFP

    Update Supply Support of LCSP

    Supply Support inputs to functional/allocated baselines

    Supply Support Plan

    Updated system supportability analysis

    Supply Support inputs to:

    Update Supply Support requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the Supply Support IMS

    Update Supply Support inputs to the LCSP

    Participate in technical and programmatic reviews

    Submit DD-61 Request for Nomenclature

    Update Supply Support Plan

    Provide support to Product Support BCA

    Supply Support inputs to:

    Update inputs to the LCCE

    Update the Supply Support IMS

    Update Supply Support inputs to the LCSP

    Execute Supply Support plan

    Proactive System Performance Management

    Supply Support inputs to LCSP

    Prognostics and Health Management

    QDR

    ECP/ECR

    Corrosion Control

    Training and Training Support

    Review ICD to identify Training and Training Support requirements and support KPPs and KSAs

    Initiate Training Systems Requirements Analysis (TSRA)

    Training Situation Analysis (TSA)

    Participate as a SME advisor to the source selection process

    Develop the preliminary training IMS

    Develop initial training inputs to LCSP

    Identify training requirements for inclusion in RFP

    Develop preliminary training concept

    Develop Funding Requirements to Execute training Concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial training concept inputs to HSI plan

    Inputs to initial system training plan

    Training Concept

    Manpower Estimate Report (MER)

    Training and Management IMS

    Training inputs to:

    Training System Alternatives Report (TSAR)

    Training System Functional Description (TSFD)

    Update Training Systems Requirements Analysis (TSRA); Training Situation Analysis (TSA); Training Situation Analysis Report (TSAR); Training Device Requirements Document (TDRD); TSFD

    Update Training Systems Plan (TSP)

    Develop Curriculum for Test Training

    Train Individuals

    Update training requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update the training IMS

    Develop training inputs to the LCSP

    Participate in technical and programmatic reviews

    Review CDD to identify training concepts

    Support planning for and conduct of system level analyses

    Develop initial training strategy

    Research DSOR/SOR impacts

    Research CORE (50/50) impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Provide Training and Training Support inputs to Product Support BCA update

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    Training strategy inputs to Capability Development Document (CDD)

    Training strategy inputs to Product Support BCA

    Updated MER

    Updates to training IMS

    Training Strategy

    Training inputs to:

    Update TSRA; TSA; TSAR; TDRD; TSFD

    Update Training Systems Plan

    Training for Test and Evaluation

    Validate Training Systems

    Procurement of Training Devices

    Develop Operators and Maintainers Training

    Update training requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the training IMS

    Develop training plan

    Updates training inputs to the LCSP

    Participate in technical and programmatic reviews

    Review updated use study

    Provide Training and Training Support inputs to Product Support BCA update

    Update HSI Plan

    Training plan inputs to Manpower Estimate (Review)

    Operational Test Agency Report of DT&E Results (to include training results)

    Training System Plan

    Updated system supportability analysis

    Training inputs to:

    Update TSRA; TSA; TSAR; TDRD; TSFD

    Update Training Systems Plan

    Develop Operational Test Training

    Update Operators and Maintainers Training

    Initial Training for Fleet

    Training equipment delivered and installed

    Update training requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the training IMS

    Update training plan

    Update training inputs to the LCSP

    Participate in technical and programmatic reviews

    Provide support to Product Support BCA

    Updates to new equipment training

    Training System Plan

    Curriculum/program of instruction (POI) for schoolhouse

    Training inputs to:

    Delivery of Curriculum for schoolhouse

    Training Course Conduct Package

    Training Project Plan

    Course Training Task List

    Training Course Control Document

    Curriculum Outline of Instruction

    Lesson Plan

    Trainee Guide

    Test Package

    Instructional Media Package

    Instructional Performance Requirements Document

    Execute Training plan

    Update inputs to the LCCE

    Update the Training IMS

    Update Training inputs to the LCSP

    Curriculum/POI

    Equipment sustainment training package

    Training inputs to LCSP

    Manpower and Personnel

    Review ICD to identify Manpower and Personnel requirements and support KPPs and KSAs

    Develop initial Manpower and Personnel inputs to LCSP

    Develop Manpower and Personnel requirements for inclusion in RFP

    Participate as a Manpower and Personnel SME advisor to the source selection process

    Develop the preliminary Manpower and Personnel IMS

    Develop Preliminary Manpower and Personnel concept in support of initial support strategy

    Develop Funding Requirements to Execute Manpower and Personnel Concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Manpower and Personnel concept inputs to HSI plan

    Inputs to initial system training plan

    Preliminary Manpower Estimate Report (MER)

    Manpower Concept

    Manpower and Personnel IMS

    Manpower and Personnel inputs to:

    Update Initial Manpower Estimate Report

    Update M&P Concepts of Employment

    Update M&P Risks, Cost Drivers, and Mitigation Plans

    Update M&P requirements to support maintenance concepts, technologies and RFP

    Participate as a SME advisor to the source selection process

    Participate in technical and programmatic reviews

    Develop M&P inputs to the LCSP

    Review CDD to identify M&P concepts

    Support planning for and conduct of system level analyses

    Develop initial M&P Strategy

    Research DSOR/SOR impacts

    Research CORE (50/50) impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Update the M&P IMS

    Provide support to M&P BCA update

    Inputs to initial system training plan

    Preliminary Manpower Estimate (MER)

    Manpower and Personnel Strategy

    Manpower and Personnel inputs to:

    Update Manpower and Personnel inputs for the LCSP

    Update Manpower Estimate Report

    Inputs to M&P Concepts of Employment

    Identify M&P Risks, Cost Drivers, and Mitigation Plans

    Create Manning Billets (military/civilian)

    Update M&P IMS

    Develop Manpower and Personnel Plan

    Update system supportability analysis

    Review updated use study

    Lead Maintenance Task Analysis review with IPSE SMEs

    Provide Manpower and Personnel inputs to Product Support BCA update

    Update Manpower and Personnel requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update HSI Plan

    Participate in technical and programmatic reviews

    Component Manning Document

    Manpower and Personnel Plan

    Updated system supportability analysis

    Manpower and Personnel inputs to:

    Update Manpower and Personnel Plan

    Update Manpower Estimate Report

    Identify M&P Risks, Cost Drivers, and Mitigation Plans

    Create Manning Billets (military/civilian)

    Update M&P inputs to the LCSP

    Update Manpower and Personnel requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE Funding Statement

    Update the Manpower and Personnel IMS

    Participate in technical and programmatic reviews

    Provide support to Product Support BCA

    Update System Training Plan (STP)

    Updated Manpower Estimate

    Updated System Training Plan (STP)

    Updated Manpower and Personnel Plan

    Manpower and Personnel inputs to:

    Update MER

    Analyze, track, monitor in accordance with LCSP

    Execute M&P (filling billet for organic or contractor support personnel)

    Fill CIV/MIL billets

    Update inputs to the LCCE

    Update the M&P IMS

    Execute Manpower and Personnel Plan

    Inputs to major system modifications to address manpower and personnel impacts related to ECP, changes to CONOPs, technical insertion and/or similar changes.

    Manpower and Personnel inputs to LCSP

    Technical Data

    Participate as a SME advisor to the source selection process

    Develop initial Intellectual Property Strategy and inputs to LCSP

    Review ICD to identify Technical Data requirements and support KPPs and KSAs

    Develop Technical Data requirements for inclusion in RFP

    Develop the preliminary Technical Data IMS

    Identify Technical Data Concept

    Develop Funding Requirements to Execute Technical Data Concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial Technical Data inputs to HSI plan

    Acquisition CyberSecurity Strategy (input to AoA)

    Consideration of technical issues

    Intellectual Property (input to LCSP)

    Technical data disposal strategy (part of TDRS input to LCSP)

    Technical Data Concept

    Technical Data IMS

    Technical Data inputs to:

    Update Technical Data Requirements/Intellectual Property Strategy

    Input Technical Data requirements into RFP

    Define Technical Data Package design

    Update Technical Manual Contract Requirements (TMCR)

    Provide support to Product Support BCA update

    Provide inputs to the product support IMS

    Participate as a SME advisor to the source selection process

    Update Technical Data inputs to LCSP

    Participate in technical and programmatic reviews

    Review CDD to identify maintenance concepts

    Support planning for and conduct of system level analyses

    Research DSOR/SOR impacts

    Research CORE (50/50) impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    Updated Technical Data Requirements for inclusion in RFP

    Acquisition CyberSecurity Strategy (input to AoA)

    Inputs to the LCCE

    Updated Intellectual Property Strategy

    Technical Data inputs to:

    Ensure development of Technical Data for support package T&E

    Validate/Verify Technical Data

    Development Design

    Review, accept and/or comment on technical data deliverables (e.g., methods, descriptions, graphical representations) for production and fabrication processes for:';>;EndMetacard

    Intellectual Property Strategy Updates (Data Rights/Data Access) input to RFP

    Participate in source selection process

    Participate in programmatic and technical reviews

    Update inputs to the LCCE to include special/unique support requirements

    Update the Technical Data IMS

    Develop Draft Fielding Plan

    Develop LRIP Requirements

    Update Technical Data inputs to the LCSP

    Intellectual Property Strategy (IPS)

    Load Publications/Manuals

    Develop Technical Data Plan

    Update system supportability analysis

    Provide Technical Data inputs to Product Support BCA update

    Update HSI Plan

    Net-centric Data Strategy (included in the Intellectual Property Strategy)

    Acquisition CyberSecurity Strategy (input to AoA)

    Technical Data Plan

    Technical Data inputs to:

    Validate/Verify Technical Data publications

    Update Intellectual Property Strategy

    Support initial fielding of technical manuals

    Accept publications/IETMs/ product data

    Provide input and/or respond to ECPs/ECRs

    Participate is programmatic and technical reviews

    Participate in Provisioning Conference

    Update inputs to the LCCE

    Update the tech data IMS

    Update Technical Data inputs to the LCSP

    Participate as a SME advisor to the source selection process

    Update Technical Data Plan

    Provide Technical Data inputs to Product Support BCA update

    Validated/Verified Technical Data

    Publications

    IETMs

    Product Data

    Engineering Change Requests/Proposals

    Configuration Changes

    Time Compliance Technical Orders (TCTO)

    Updated Technical Data Plan

    Technical Data inputs to:

    Execute Technical Data Plan

    Verify Updated Publications

    Dispose/archive of publications from all systems at end of Principle End Item (PEI) service life

    Update Technical Data inputs to the LCCE

    Intellectual Property Strategy (IPS)

    Update the Technical Data IMS

    Update Technical Data inputs to the LCSP

    Engineering Change Requests/Proposals

    Configuration Changes

    Time Compliance Technical Orders (TCTO)

    Archived publications/technical data

    Technical Data inputs to LCSP

    Support Equipment

    Review ICD to identify Support Equipment requirements and support KPPs and KSAs

    Identify support equipment requirements for inclusion in RFP

    Participate as a Support Equipment SME advisor to the source selection process

    Develop preliminary funding requirements for support equipment

    Develop the preliminary support equipment IMS

    Develop the RFP for Special SE technology development contract

    Provide Support Equipment inputs to LCSP

    Develop preliminary support equipment concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial support equipment concept inputs to HSI plan

    Existing/common support equipment requirements

    List of existing/common support equipment

    Support equipment IMS

    Support Equipment Concept

    Support Equipment inputs to:

    Update support equipment requirements for inclusions in RFP

    Participate as a SME advisor to the source selection process

    Update the support equipment IMS

    Develop support equipment inputs to LCSP

    Participate in technical and programmatic reviews

    Review CDD to identify support equipment concepts

    Support planning for and conduct of system level analyses

    Develop initial support equipment strategy

    Review maintenance concept and maintenance engineering analysis

    Research CORE (50/50) impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Provide Support Equipment inputs to product support BCA update

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:

    Inputs to initial system training plan

    Support Equipment Strategy

    Support Equipment inputs to:

    Update support equipment requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the support equipment IMS

    Develop support equipment Plan

    Update support equipment inputs for the LCSP

    Participate in technical and programmatic reviews

    Update system supportability analysis

    Review updated use study

    Provide Support Equipment inputs to Product Support BCA update

    Update HSI Plan

    Support equipment Plan

    Draft Fielding Plan

    Updated system supportability analysis

    Support Equipment inputs to:

    Update support equipment requirements for inclusions in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the support equipment IMS

    Update Support Equipment plan

    Update Support Equipment inputs for the LCSP

    Participate in technical and programmatic reviews

    Award Special SE production contract

    Conduct Special SE production contract Start of Work meeting

    Conduct Supportability Demonstration

    Evaluate OT and Supportability Demonstration report

    Conduct provisioning conference

    Approve fielding

    Provide support to Product Support BCA

    Field General and Special SE (if applicable)

    Updated Support Equipment Plan

    Support Equipment inputs to:

    Execute Support Equipment Plan

    Update inputs to the LCCE

    Update the Support Equipment IMS

    Update Support Equipment inputs for the LCSP

    Monitor Support Equipment

    Update Special Support Equipment documentation

    Proactive System Performance Management

    End of PEI Life Cycle (if not, initiate PIP/SLEP)

    If end of Life-Cycle; initiate disposal instruction for Special SE

    Dispose of Special SE

    Updated system supportability analysis

    Support Equipment inputs to LCSP

    Prognostics and Health Management

    QDR

    ECP/ECR

    Corrosion Control

    Computer Resources

    Review ICD to identify Computer Resources requirements and support KPPs and KSAs

    Participate as a SME advisor to the source selection process

    Develop the preliminary Computer Resources IMS

    Develop initial Computer Resources inputs to LCSP

    Develop Computer Resources requirements for inclusion in RFP

    Develop preliminary Computer Resources concept

    Develop Funding Requirements to Execute Computer Resources concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial Computer Resources concept inputs to HSI plan

    Computer Resources IMS

    Computer Resources concept

    Computer Resources inputs to:

    Update computer resources requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update the Computer Resources IMS

    Develop Computer Resources inputs to the LCSP

    Participate in technical and programmatic reviews

    Review CDD to identify Computer Resources concepts

    Support planning for and conduct of system level analyses

    Develop initial Computer Resources strategy

    Research DSOR/SOR impacts

    Research CORE (50/50) impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Provide Computer Resources and Support inputs to Product Support BCA update

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    Computer Resources Strategy

    Computer Resources inputs to:

    Update Computer Resources requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the Computer Resources IMS

    Develop Computer Resources Plan

    Update Computer Resources inputs to the LCSP

    Participate in technical and programmatic reviews

    Update system supportability analysis

    Review updated use study

    Provide Computer Resources inputs to Product Support BCA update

    Update HSI Plan

    Computer Resources Plan

    Updated system supportability analysis

    Computer Resources inputs to:

    Update Computer Resources requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the Computer Resources IMS

    Update Computer Resources plan

    Update Computer Resources inputs to the LCSP

    Participate in technical and programmatic reviews

    Provide support to Product Support BCA

    Updated Computer Resources Plan

    Updated system supportability analysis

    Computer Resources inputs to:

    Update inputs to the LCCE

    Update the Computer Resources IMS

    Update Computer Resources inputs to the LCSP

    Proactive System Performance Management

    Execute Computer Resources Plan

    Computer Resources inputs to LCSP

    Prognostics and Health Management

    QDR

    ECP/ECR

    Corrosion Control

    Packaging, Handling, Storage, and Transportation

    Review ICD to identify PHS&T requirements and support KPPs and KSAs

    Develop initial PHS&T inputs to LCSP

    Identify PHS&T requirements for inclusion in RFP

    Participate as a PHS&T SME advisor to the source selection process

    Develop the preliminary PHS&T IMS

    Develop preliminary PHS&T concept

    Develop Funding Requirements to Execute PHS&T Concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial PHS&T concept inputs to HSI plan

    PHS&T Concept

    PHS&T IMS

    PHS&T inputs to:

    Update PHS&T requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update the PHS&T IMS

    Develop PHS&T inputs to the LCSP

    Participate in technical and programmatic reviews

    Review CDD to identify PHS&T concepts

    Support planning for and conduct of system level analyses

    Develop initial PHS&T strategy

    Research DSOR/SOR impacts

    Research CORE (50/50) impacts

    Conduct supportability analysis to influence design

    Complete 1st iteration of the RCM Analysis

    Update RAM-C Rationale Report

    Provide PHS&T inputs to Product Support BCA update

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    PHS&T Strategy

    PHS&T inputs to:

    Update PHS&T requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the PHS&T IMS

    Develop PHS&T plan

    Update PHS&T inputs to the LCSP

    Participate in technical and programmatic reviews

    Update system supportability analysis

    Review updated use study

    Provide PHS&T inputs to Product Support BCA update

    Update HSI Plan

    PHS&T Plan

    Updated system supportability analysis

    PHS&T inputs to:

    Update PHS&T requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the PHS&T IMS

    Update PHS&T plan

    Update PHS&T inputs to the LCSP

    Participate in technical and programmatic reviews

    Provide support to Product Support BCA

    Updated PHS&T Plan

    PHS&T inputs to:

    Update inputs to the LCCE

    Update the PHS&T IMS

    Update PHS&T inputs to the LCSP

    Execute PHS&T Plan

    Proactive System Performance Management

    PHS&T inputs to LCSP

    Prognostics and Health Management

    QDR

    ECP/ECR

    Corrosion Control

    Facilities and Infrastructure

    Identify Facilities and Infrastructure requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Develop the preliminary Facilities and Infrastructure IMS

    Review ICD to identify Facilities and Infrastructure requirements and support KPPs and KSAs

    Develop initial Facilities and Infrastructure inputs to LCSP

    Develop preliminary Facilities and Infrastructure concept

    Develop Funding Requirements to Execute Facilities and Infrastructure Concept

    Participate in initial use study

    Prepare Initial input to RAM-C Rationale Report

    Develop Initial Facilities and Infrastructure concept inputs to HSI plan

    Facilities and Infrastructure Concept

    Facilities and Infrastructure IMS

    Facilities and Infrastructure inputs to:

    Update Facilities and Infrastructure requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update initial Facilities and Infrastructure inputs to the LCCE

    Update the Facilities and Infrastructure IMS

    LCSP

    Review CDD to identify Facilities and Infrastructure concepts

    Support planning for and conduct of system level analyses

    Develop initial Facilities and Infrastructure strategy

    Research DSOR/SOR impacts

    Research CORE (50/50) impacts

    Preventive and corrective maintenance tasks identified using RCM and CBM+

    Review FMECA and LORA data to support Facilities decisions

    Provide Facilities and Infrastructure inputs to Product Support BCA update

    Participate in technical and programmatic reviews

    Analyze System Use Study/Mission Profile/CONOPS Summary to extract:';>;EndMetacard

    Facilities and Infrastructure Strategy

    Facilities and Infrastructure inputs to:

    Update Facilities and Infrastructure requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the Facilities and Infrastructure IMS

    Develop Facilities and Infrastructure plan

    Update Facilities and Infrastructure inputs to the LCSP

    Participate in technical and programmatic reviews

    Update system supportability analysis

    Review updated use study

    Provide Facilities and Infrastructure inputs to Product Support BCA update

    Update HSI Plan

    Facilities and Infrastructure Plan

    Updated system supportability analysis

    Facilities and Infrastructure inputs to:

    Update Facilities and Infrastructure requirements for inclusion in RFP

    Participate as a SME advisor to the source selection process

    Update inputs to the LCCE

    Update the Facilities and Infrastructure IMS

    Update Facilities and Infrastructure plan

    Update Facilities and Infrastructure inputs to the LCSP

    Participate in technical and programmatic reviews

    Provide support to Product Support BCA

    Updated Facilities and Infrastructure Plan

    Facilities and Infrastructure inputs to:

    Update inputs to the LCCE

    Update Facilities and Infrastructure inputs to the LCSP

    Execute Facilities and Infrastructure Plan

    Update the Facilities and Infrastructure IMS

    Proactive System Performance Management

    Facilities and Infrastructure inputs to LCSP

    Prognostics and Health Management

    QDR

    ECP/ECR