    A sequence of discrete work packages and planning packages (or lower-level tasks/activities) in the network that has the longest total duration through an end point that is calculated by the schedule software application. Discrete work packages and planning packages (or lower-level tasks/activities) along the CP have the least amount of float/slack (scheduling flexibility) and cannot be delayed without delaying the finish time of the end point effort. Essentially, CP has the same definition as Program CP with the exception that the end point can be a milestone or other point of interest in the schedule. For example, a CP could be run to Preliminary Design Review (PDR), Critical Design Review (CDR), and/or First Flight within a contract.